Schedule

The schedule may change, especially if we encounter unforeseen difficulties.

The current schedule is:

2018

May 16 – Kjellstrom and Lee given formal go ahead to proceed

May 24  – Building Permit Issued

May 27 – First service in Scott Hall

June 4  – Begin site preparation

June 11 – Start preparatory work in Chapel, Chancel and Nave

August 3 – Complete Footings for structural steel

September 14 – Structural steel installed

October 19 – Air handler installed in tower

November 16 – New tile installed and existing tile refinished

December 14 – Chapel construction completion

2019

January 18 – Railings, Lights A/V, furnishings installed

January 18 – Complete Painting

January 24  – Chancel, Nave, Narthex and Gallery construction completion